How does a comunicat diferit differ from a comunicat immediat?
The comunicat diferit (deferred-effect notice) is an intermediate regime between the comunicat immediat and a major-works licence. Both notices include technical documents signed by a professional and a suitability report; the difference is timing. With the immediate notice you can start the day after filing, once the ICIO tax and fee are paid. With the deferred notice, work may only start once the one-month period during which the council can review and object has passed (ORPIMO, arts. 49 and 50).
Which regime your project needs is decided by the technician under the municipal ordinance for your specific address. Lists of works and timescales change, so check any figure on the council’s e-office at the time of filing.
Which works usually go through a comunicat diferit?
Under the ORPIMO (art. 3.3), the deferred notice covers type I minor works: renovation that partly affects the building’s structure without changing its use, consolidation with partial work on the structure, interior renovation of two or more homes in the same building, dividing ground-floor premises, installing a lift inside the building and works on level D buildings or in protected ensembles, among others. Reconfiguring a single flat, removing and building non-structural partitions or moving the kitchen or bathroom with new drainage runs is not a deferred notice: it is a comunicat immediat (art. 3.4.b).
The line is drawn mainly by how far the structure is affected. Replacing tiles and sanitaryware in the same positions goes through the assabentat. Cutting a localised opening in a load-bearing wall is an immediate notice with calculations; partial work on the structure is a deferred notice; only work on the whole structure needs a major-works licence. We explain how to classify your project in our guide to minor versus major works.
Which documents are filed with a comunicat diferit?
The core of the file is technical documentation signed by a competent professional: a description of the works, drawings of the existing and proposed layout, and a budget. It comes with a responsible declaration, the applicant’s and property details, community consent where required and construction-waste paperwork. Fees and the construction tax are paid; the council confirms the amounts.
We cover the full document list for each procedure in a separate guide, and who may sign the project in another. What matters here: the documents must describe exactly what will be built.
What can you do during the comunicat diferit waiting period?
While the review period runs, strip-out cannot begin. That time is not wasted, though. It is the slot for everything that has to happen before the works anyway: signing the contract, approving material samples, ordering windows, kitchen and slow-to-make furniture, agreeing noisy-work hours and lift use with the property manager.
A well-planned renovation starts on the day the period ends, with materials already on order. A poorly planned one starts on the same day, but the crew spends its first weeks waiting for deliveries.
What can go wrong with a comunicat diferit?
The council may request corrections or extra documents. In practice the clock moves until you reply. The usual reasons are an incomplete file, discrepancies between drawings and written description, or missing community consent where it was needed.
The second problem appears on site. If during the works someone decides to move another partition or the bathroom and the documents stay as they were, the works no longer match what was filed. After an inspection or a neighbour’s complaint, that becomes your problem. Any layout change is checked against the filed documents first.
Which procedure does opening up a kitchen in an Eixample flat need?
In an Eixample flat, the owners want to open the kitchen to the living room and add a second bathroom. If the wall between kitchen and living room is not load-bearing, it is a typical comunicat immediat case, not a deferred one: it is a layout change in a single home. But in Eixample buildings some interior walls are load-bearing. If that wall is one of them, a localised opening with its beam is still a comunicat immediat, with structural calculations; if the works affect the structure more widely, it moves to a comunicat diferit; and a major-works licence only comes in if the intervention covers the whole structure. Find out before filing, with the technician on site, not after the wall is opened.
A practical rule for flats like these: until the technician has confirmed the regime, do not give the crew a start date, do not book furniture removal for a specific day and do not sign a temporary rental without a margin. Moving from one regime to the other changes the paperwork and also the time before work can start, so plan family life around the slower scenario.
What should you send BCN YARD to find out which procedure your works need?
Send us the floor plan and a description of what you want to change. Together with the technician we will work out the regime, prepare the file so that what is filed matches what gets built, and use the waiting period for orders. We reply within an hour, in Spanish and Russian.
Frequently asked questions
What is the difference between a comunicat diferit and a comunicat immediat?
Both include technical documents signed by a competent professional and a suitability report. With a comunicat immediat, work can start the day after filing, once the tax and fee are paid. With a comunicat diferit, work starts only after the one-month period in which the town hall can review the documents and object. Which regime applies is decided by the technician under the municipal ordinance for that address.
Does removing a load-bearing wall fall under a comunicat diferit?
It depends on the scope. Under the ORPIMO, cutting a localised opening in a load-bearing wall is type II minor works and goes through a comunicat immediat, with a project and calculations; if the renovation partly affects the structure, it is type I and goes through a comunicat diferit; only work on the building’s whole structure needs a major works licence. Moving non-structural partitions or relocating the kitchen or bathroom in a flat is a comunicat immediat, and replacing tiles and sanitaryware in the same places is an assabentat.
What documents go with a comunicat diferit?
A comunicat diferit is built on technical documents signed by a competent professional: a description of the works, existing and proposed drawings and a budget. Added to these are a responsible declaration, applicant and property details, comunidad consent where needed and construction waste management documents. Fees and the building works tax are also paid.
What happens if I change the layout filed in the comunicat during the works?
If during the works you move another wall or the bathroom while the filed documents stay the same, the works no longer match what was notified, and in an inspection or after a neighbour's complaint that becomes your problem. Any layout change is checked against the filed package first. The town hall may also request corrections, and the period shifts until you reply.