What is the difference between a fixed-price and a measured quote?
A fixed-price quote (presupuesto cerrado) is one total price for a scope described in advance. A measured quote (por medición) sets unit rates, for example per square metre of tiling or per linear metre of partition, and the total is calculated from what is actually built.
The first gives predictability but needs a finished design before signing. The second is fairer when quantities cannot be known in advance, but you only see the final figure at the end. For a flat in an older building, a mixed system usually fits best. The choice depends not on how much you trust the contractor but on how much is known about the property before work starts.
What must be ready before signing a fixed-price quote?
A fixed-price quote holds up only as well as the scope description does. For it to work, before signing you need dimensioned plans, elevations of the bathrooms and kitchen, an electrical layout and the chosen tile, sanitaryware, door and flooring models with product references.
If the quote says "bathroom tiling" with no reference and no area, the price is fixed only on paper. The first time you pick a tile dearer than the one the contractor had in mind, it becomes an extra. Any change after signing is recorded separately, with its price and its effect on the timeline.
This system suits finish-only renovations with no walls moving, and projects where everything has been chosen in advance.
How does a measured quote work?
A measured quote contains unit rates and estimated quantities. The total is a guide, not a commitment. You pay for what is actually built.
The key question is how things are measured. Agree the rules beforehand: whether door and window openings are deducted from the tiling area, whether cuts are charged separately, how reveals, ceiling bulkheads and wall chases are counted. If the rules are not written down, two people will measure different figures in the same bathroom, and both will be partly right.
It is best to measure jointly, stage by stage, and sign a record while everything is still visible. A wiring chase cannot be measured once it has been plastered over.
Why does a mixed system suit an older flat?
In an Eixample flat you cannot know in advance what state the beams under the parquet are in, how many centimetres of levelling layer will have to come off, or what the old tiles are hiding. An honest quote for that job comes in two parts.
Everything that can be described goes at a fixed price: partitions to plan, electrics to layout, sanitaryware to specification, finishes to the chosen materials.
Everything that depends on opening up goes at unit rates with estimated quantities: repairing or strengthening beams, levelling beyond the thickness allowed for, replacing sections of the stack. And the approval route is written in: the contractor shows the problem, photographs it, states the quantity at the unit rate, and you confirm in writing before work starts.
Where does each type of quote let you down?
A fixed price fails when it is signed without a design. Either the contractor builds in a cushion for the unknown and you overpay, or prices the bare minimum and recovers the difference through extras.
A measured contract fails when unit rates are agreed but measurement rules and caps are not. The total climbs with no ceiling, and the only way to control it is to be on site all day.
Both fail when it is unclear how new work not in the quote will be priced. Those rates, or the procedure for setting them, belong in the contract. What to do once a budget has already spiralled is covered in a separate article.
How does BCN YARD price a renovation?
We prepare the quote after the site visit and measurements, item by item. Whatever can be defined in advance is fixed; whatever depends on opening up is split out as separate items with unit rates and an approval procedure. Payments follow the contract, in stages tied to completed work.
For reference, a full renovation with us starts at €1,000/m² excluding IVA at Premium level, €2,000/m² at Luxury and €3,000/m² at Signature. Each project has one person in charge, in Russian or Spanish. We reply to enquiries within an hour.
Frequently asked questions
When does a fixed-price quote make sense for a renovation?
A fixed-price quote suits finish-only renovations with no walls moving, and projects where everything is chosen in advance. Before signing you need dimensioned plans, bathroom and kitchen elevations, an electrical layout and the tile, sanitaryware, door and flooring models with references. Without that description, the price is fixed only on paper.
Which measurement rules should be agreed in a measured quote?
In a measured quote, agree in writing whether door and window openings are deducted from tiling, whether cuts are charged separately, and how reveals, ceiling bulkheads and wall chases are counted. It is best to measure jointly, stage by stage, and sign a record while everything is still visible.
Which type of quote is best for renovating an Eixample flat?
A mixed system usually suits an Eixample flat best. What can be described, such as partitions, electrics, sanitaryware and finishes, goes at a fixed price. What depends on opening up, such as beams, extra levelling or sections of the stack, goes at unit rates with estimated quantities and written approval before the work.
How is unforeseen work approved during a renovation?
Unforeseen work is approved through a procedure written into the contract: the contractor shows the problem, photographs it, states the quantity at the unit rate, and the client confirms in writing before work starts. If the contract does not set how new work will be priced, both fixed-price and measured quotes fail.