BCNYARD■
+34 631 09 68 62WhatsAppTelegram
ESENRU

Blog

Before strip-out: document the renovation scope

Before strip-out, three things are recorded: what goes, what stays and the state of everything around it. A marked plan, a list and dated photos prevent disputes.

Building services · work in progress · house with a pool
BCN YARD project · House with a pool

What needs recording before strip-out begins?

Before strip-out, three things need recording: exactly what is removed, what stays or comes out to be reinstated, and the condition of everything around it — stairwell, lift, neighbours’ flats. A floor plan marked up in colour, a short room-by-room list and dated photos and video are enough.

“We’re replacing the whole kitchen” says nothing about the kitchen door, the radiator under the window or the socket that feeds the next room. Two weeks into the works, those details turn into arguments about what was in scope and who pays for what.

How do you list what is removed, kept and reinstated?

Every element goes in one of three columns. Remove, and take away. Keep in place, and protect with film or boxing. Take out and reinstate: internal doors, radiators, period door handles, cornicing restored separately.

On site, the same is marked with masking tape directly on each element: green stays, red goes. For the reinstate column, decide where things are stored during the works and who is responsible for them. What is worth keeping in a renovation is covered in a separate guide.

How do you record the condition of the stairwell, lift and neighbours' flats?

Photograph the entrance hall, the inside of the lift, the flights of stairs up to your floor and the neighbours’ door. If you can, arrange with the neighbour below to look at their ceiling under your bathroom and kitchen: old stains and cracks are recorded before work starts, not after the first complaint.

Email the photos to the property manager. A dated email beats a folder on your phone: a month later nobody argues about whether the scratch on the lift door was already there. Note the water and electricity meter readings while you are at it.

Which shared services run through your flat, and how do you locate them?

In an apartment building, shared soil stacks and water risers often run through your flat, and sometimes cables or gas supplying the neighbours. Before strip-out, mark on the plan where the stacks, stopcocks and consumer unit are, and what runs through the walls that are coming down.

Cutting a pipe that feeds the flat upstairs is the mistake that turns day one of strip-out into an emergency call. If there is any doubt about what a pipe is, work at that spot stops until it has been checked.

What must not be judged by eye during strip-out?

In Eixample buildings some interior walls are load-bearing, and a partition that looks thin may be carrying the floor above. Neither a photo nor the wall’s thickness is licence to remove it: a professional determines what each wall does, and that is settled before strip-out, in the project.

The stop rule: if something unexpected turns up behind the plaster or under the floor — a rotten beam, lead pipes, material that looks like fibre cement — work in that area stops. Photos, a visit from the technician, a written decision, and only then do things continue. Extra work is priced and approved before it is carried out, under the same procedure as any other change to the renovation.

What should you do if an old floor turns up under the covering?

A typical Eixample scenario: under the laminate or lino there is old hydraulic mosaic tile. Sometimes in good condition, sometimes half broken. The “what do we do if we find it” decision is made before strip-out: keep and restore it in one room, lift it and reuse it as a feature, or remove it. Otherwise a crew whose instructions say “remove floors” will simply follow the instructions.

The same logic applies to timber floor joists, old doors and cornicing hidden above a suspended ceiling. Better to decide in advance what happens to a find than to decide on site with the schedule pressing.

How do you organise protection and rubble removal?

Agree protection of common areas, the rubble route and the skip location with the property manager, and get a permit from the ajuntament for a skip in the street. We carry out strip-out within the agreed scope, with one person responsible for the site, and report every find before anything is added to the works. Send us the floor plan and photos: we reply within an hour, in Spanish or Russian.

Frequently asked questions

What should be documented before renovation strip-out?

Before strip-out, three things are recorded: exactly what is removed, what stays or comes out to be reinstated, and the condition of the stairwell, lift and neighbours' flats. A floor plan marked up in colour, a short room-by-room list and dated photos and video are enough.

Why email photos of the building to the property manager?

A dated email to the property manager beats a folder on your phone: a month later nobody argues about whether a scratch on the lift door was already there. Photograph the entrance hall, the lift, the stairs and the neighbours' door, and check with the neighbour below their ceiling under your bathroom and kitchen.

What should happen if something unexpected turns up during strip-out?

If something unexpected turns up behind the plaster or under the floor, such as a rotten beam, lead pipes or material that looks like fibre cement, work in that area stops. Photos are taken, the technician visits, a decision is made in writing, and only then does work continue. Extra work is priced and approved before it is done.

Can you tell whether a wall is load-bearing from its thickness?

No. In Eixample buildings some interior walls are load-bearing, and a partition that looks thin may be carrying the floor above. Neither a photo nor the wall's thickness is licence to remove it: a professional determines what each wall does, and that is settled in the project, before strip-out.

How is it marked on site what stays and what goes?

On site each element is marked with masking tape: green stays, red goes. The list has three columns: remove, keep in place protected with film or boxing, and take out to reinstate, such as doors, radiators or cornicing. For items being reinstated, decide where they are stored and who is responsible.

Sources

Royal Decree 105/2008 on construction and demolition waste, art. 4.1(b)

Royal Decree 396/2006 on work with asbestos exposure risk, art. 10.2

Barcelona City Council: Tax Ordinance 3.4, rubble bags and skips

BCN YARD / Contact

Tell us what you have in mind.

Service area: Barcelona and the wider province.

  • Own crew and trusted subcontractors
  • We speak Russian and Spanish
  • Reply within an hour
  • Staged payments under contract
  1. 01Property
  2. 02Services
  3. 03Size and location
  4. 04Timing
  5. 05Contact
Property