How do you plan deliveries and storage during a flat renovation?
Deliveries are planned around three things: the route each item takes from the street to where it is installed, free storage space on site, and the person who receives and checks the goods. Large items are only ordered once the route has been measured, and materials arrive when their area is ready, not when the supplier happens to have a sale on.
In a flat in an older Barcelona building, all three are harder than they look. Here is what to check, and in what order.
How do you check a large item can get from the street to where it goes?
Measure the whole way in. Where the van can stop, and the hours of the loading bay, which in the Eixample is a problem in its own right. The width of the street door, the internal size of the lift car and its door, the turns in the staircase, the flat’s front door and the turn in the hallway.
The most awkward items are a three-metre stone worktop, shower screen glass, large-format porcelain slabs, a bathtub, an American-style fridge, the sofa and wardrobe panels. A worktop can fit in the kitchen and still not get up the stairs. The solutions are well known: split the worktop into two pieces with a joint positioned at design stage, assemble furniture on site, or lift large items through a window or balcony with a furniture hoist. A hoist on the street needs a permit from the Ajuntament to occupy the pavement, and that has to be arranged in advance.
What needs agreeing with the comunidad and the neighbours?
Building rules often limit the hours the lift can be used for materials and require the lift car and entrance hall to be protected. Tell the building administrator and the concierge early and agree a schedule. A skip bag or container on the street also needs a permit. Damage to common areas is paid for by whoever caused it, and arguing about that at the end of a renovation is unpleasant for everyone.
How do you store materials on site without damage or getting in the way?
A flat under renovation has very little free space. Set aside as storage the area that will be worked on last, and do not turn a room that is about to be renovated into an indefinite warehouse.
Spread the weight. A pallet of tiles on one spot of an old timber-joisted floor is not a good idea. Parquet needs acclimatising according to the manufacturer’s instructions, but it should not be in the flat while plaster and screeds are drying, or the boards will take on moisture. Sanitaryware and glass are kept in a protected corner, and appliances stay in their packaging until installation.
When should deliveries arrive on site?
The best warehouse is the supplier’s. Ask how long they will hold paid-for goods free of charge, and tie delivery to the construction stage rather than the purchase date. Check manufacturing lead times and delivery dates against the works schedule: an order either arrives on time or becomes dead weight under the crew’s feet.
Tiles are ordered in a single batch, with an allowance for cuts and future repairs, typically 5 to 10 % depending on the layout. Getting the same shade and calibre later can be impossible.
Who receives deliveries on site, and what should they check?
Appoint one person to receive deliveries. They check the product reference, batch, quantity and any visible damage, photograph problems and only then sign the delivery note, adding “received subject to inspection” if in doubt. The window for claiming hidden damage from a supplier can be short, so ask about it when you order.
Delivered does not mean installed. Keep a simple list with statuses: ordered, delivered, accepted, installed. That shows what work is really left and what is still to arrive.
How much material arrives at a flat during a renovation?
Take the scale of the Urgel flat in the Eixample: 109.80 m², four bedrooms, two bathrooms, an open kitchen and herringbone parquet. A flat that size receives parquet, tiles for two bathrooms and the kitchen, sanitaryware, kitchen units, internal doors, appliances and light fittings: several pallets and dozens of boxes. If all of that turns up in the first month, there is nowhere left to work.
That is why on our projects deliveries follow the construction stages, and the site manager receives them. Send us your floor plan and a list of what you have already ordered or chosen. We reply within an hour, in Russian or Spanish.
Frequently asked questions
What can you do if a stone worktop will not fit up the stairs?
The usual solutions are splitting the worktop into two pieces with a joint whose position is decided in the design, assembling furniture on site, or lifting large items through a window or balcony with a removals hoist. A hoist in the street needs a public highway occupation permit from the City Council, which must be requested in good time.
Where are materials stored during a flat renovation?
In the area that will be renovated last, without turning a room due to be worked on soon into a store. Spread the weight: a pallet of tiles on one spot of an old timber-beam floor is a bad idea. Parquet should not be in the flat while plaster and screeds are drying, because the wood absorbs moisture.
How much extra tiling should you order for a renovation?
Tiles are ordered in a single batch, with a margin for cuts and future repairs, usually between 5 and 10% depending on the layout. Ordering one batch matters because later it may be impossible to get the same shade and calibre.
What should be checked when receiving materials on site?
One designated person checks the reference, batch, quantity and visible damage, photographs any issue and only then signs the delivery note, marked "received with reservations" if in doubt. The deadline to claim hidden damage can be short, so ask when ordering. Keep a list with statuses: ordered, delivered, received, installed.
Sources
Barcelona City Council: Tax Ordinance 3.10, use of the public highway (removals, lifting platforms)
Barcelona City Council: Tax Ordinance 3.4, street-occupation licence for rubble bags and skips