What should the client check at the structural stage?
At the structural stage the client is not checking concrete strength but their own decisions, which are about to become irreversible: opening sizes, penetrations for services, floor and ceiling levels, supports for future equipment. Once the concrete is poured, any of these can only be changed by drilling, cutting and recalculating.
Structural assessment is done by the architect and the arquitecto técnico on the site direction team. Your job is to arrive at the meeting with the plan and a list of questions before each level is poured, not after.
Which decisions become permanent once the concrete is poured?
Door and window openings. If you have changed your mind and want the terrace sliding door 60 cm wider, today it is a drawing revision; in a month it is a new lintel and a calculation.
Penetrations and sleeves for services. Drainage, heat-recovery ventilation, air-conditioning ducts and pipes running from the pool to the plant room all pass through slabs and beams. A missed penetration gets drilled later through the finished structure, and that is not always permitted.
Levels. Underfloor heating, an acoustic layer and the floor finish add up to centimetres that must be allowed for in the slab level.
The stair opening, a lift pit, rooflights, fixings for a pergola or supports for solar panels on the roof.
How are a pool, solar panels and services coordinated with the structure?
Our private house with a pool, built from start to finish between 2022 and 2024, shows how many systems converge in the structure. In a house like that, pipes run from the pool shell to the plant room, cabling from the solar panels comes down from the roof to the inverter, and the climate system needs routes between floors.
At each crossing, where the pipe or cable goes is decided in advance so the penetration lands in a permissible part of the structure. If the services decisions have not been made by the time the frame goes up, it is easier to delay the pour by a week than to look for a workaround later.
What should you ask at the site meeting before a pour?
Which level is being reinforced now and when is the pour planned? Have penetrations and sleeves been checked against the latest services drawings? Which of my decisions need confirming before the pour? What checks does the site direction team carry out before concreting, and how are they recorded?
If you spot a difference from the drawing, mark the location on the plan, photograph it and pass the question to the person in charge. Do not ask the workers on site to move or add anything: any change to the structure is approved by the site direction team.
What should you photograph before a pour, and why?
The most useful photos are taken the day before the pour: reinforcement, cast-in fixings, sleeves, pipes and cables that will end up inside the slab. Shoot with a tape measure in frame and reference to gridlines or walls, and note the level and zone.
Years later, those pictures will tell you where it is safe to drill, where the underfloor heating pipe runs and where the cable from the panels went. A photo cannot tell you about structural quality, though: it shows positions, not strengths or test results.
Why measure the structure after striking formwork before ordering windows and kitchen?
Once the formwork is removed comes a moment that is often forgotten. The actual dimensions of openings, heights and penetrations are checked against the drawing and recorded. Windows, sliding systems, the staircase, the lift and the kitchen are ordered from those measurements, not from the design: a couple of centimetres between drawing and concrete is normal, and a window that has already been made cannot be adjusted to it.
The same survey shows whether everything on the client's list made it into the structure: the sleeves are in place, the stair opening is the right size, the pergola fixings are where they were expected. If something is missing, now is the time to sort it out, before the walls and facade begin.
How do you visit a site safely at the structural stage?
A site at the structural stage is at its most dangerous: open slab edges, formwork, reinforcement, a working crane. Come by appointment, accompanied by the person in charge, in a hard hat and closed shoes, and do not go up where there is no edge protection.
On our projects one person is in charge, collects your questions and takes them to the right professional. Visits are planned around the stages, when there is something to check before a pour. We work in Russian and Spanish, with staged payments under the contract. We reply to enquiries within an hour.
Frequently asked questions
What should a homeowner check during the structural stage of their house?
At the structural stage the homeowner is not checking concrete strength but their own decisions before they become irreversible: opening sizes, service penetrations, floor and ceiling levels and supports for future equipment. Structural assessment is done by the architect and the arquitecto técnico on the site direction team. The useful thing is to bring questions before each pour.
Can a window opening be widened after the concrete is poured?
After the pour, widening a window or door opening is no longer a drawing revision but a new lintel and a calculation. Before the pour, making a terrace sliding door 60 cm wider is just a drawing change. The same goes for missed service penetrations: later they have to be drilled through the finished structure, and that is not always permitted.
Why photograph the structure before the pour?
Photos taken the day before the pour record reinforcement, cast-in fixings, sleeves, pipes and cables that will end up inside the slab. Take them with a tape measure in frame and reference to gridlines or walls. Years later they show where it is safe to drill and where pipes run, although a photo does not certify structural quality: it shows positions, not strengths.
When are openings measured to order windows for a new house?
Openings are measured after the formwork is struck, comparing actual dimensions with the drawing. Windows, sliding systems, stairs, lift and kitchen are ordered from those measurements, not from the design, because a couple of centimetres between drawing and concrete is normal. The same survey confirms that sleeves, the stair opening and fixings are where expected.