A house’s foundations: what to expect at this stage

The engineer sets the foundation type from the soil data; the owner's job is to plan service entries early and keep records of what gets buried.

Façade · work in progress · house with a pool
BCN YARD project · House with a pool

What happens at the foundation stage, and what is up to you?

The owner does not pick the foundation type; the engineer sets it based on the geotechnical study. The client's job at this stage is different: do not move the house on the plot, decide early where service entries will pass through the foundations, and get photos and records of everything that will be buried within a few weeks.

On site you will see an excavation or trenches, reinforcement cages and concrete being poured. It looks rough and quick. But this is where mistakes are made that later cannot be seen or cheaply put right.

What decides a house's foundation type?

Pad footings under columns, strip footings under walls, a raft, piles: the choice comes from calculations based on the actual bearing capacity of the ground on your plot. The neighbour had a raft and their house is fine is not an argument. Two plots across a road can be very different.

Take a house in Castelldefels. Near the sea the ground can be sandy with a higher water table; on the Garraf slopes you may find rock next to made ground. In the first case the concern is settlement and water; in the second, how to bear the house on mixed ground. The difference between a topographic survey and a geotechnical study is covered in its own article; here it is enough to know that foundations are not designed without a geotechnical report.

In what order is a foundation built on site?

First comes setting out: the surveyor marks the house grid on the plot. Then excavation for footings or raft, a blinding layer so the steel does not sit on soil, and placing reinforcement and formwork. Before pouring, the site's technical supervision team checks the steel: bar sizes, spacing, cover and the starter bars for the columns. Only then is concrete ordered.

If you visit the site, go on the day the reinforcement is inspected. It is the last moment you can see what ends up inside.

What must be built into the foundation before the concrete pour?

Water, power and telecoms supplies, drainage, and pipes to the pool and garden all pass through or under the foundations. Sleeves are set for them in the right places and at the right depth in advance. Drilling finished concrete foundations is not always possible, and where it is, it is expensive and needs the engineer's approval.

The earthing electrode goes into the foundations too. If there is a basement or a buried plant room, waterproofing of the retaining walls and perimeter drainage are settled now. On a house with a pool and solar panels (we built one such private house through the full cycle in 2022 to 2024), the routes to the pool and plant area are fixed before the pour; afterwards there is simply no way through.

How long does foundation concrete need before it takes load?

Concrete gains strength gradually, and for the first days after pouring it is cured: in hot weather it is watered or covered so the surface does not dry out and crack, in rain the fresh pour is protected. When the foundations can take the next structure is decided by the technical supervision team, not by the schedule.

If a contractor offers to save a week at this stage, ask who will sign off that decision. A week saved is not worth cracks in the frame.

What happens if the ground differs from the geotechnical report?

A geotechnical study relies on a handful of boreholes, while the excavation opens up the whole plot. If digging finds an old foundation, a pocket of soft ground, water or rock where none was expected, the engineer decides: deepen the footings, replace the soil or change the foundation type. That changes the quantities and the price.

Agree in advance how such changes are handled: who records the finding, how quickly you receive a costing and who approves it. Then a surprise on site becomes a clear decision rather than an argument.

Which foundation records should you collect?

Ask the contractor for photos of the reinforcement before the pour, with a tape measure in shot, the concrete delivery notes showing mix and arrival time, test results for any samples taken, and the site supervision notes for this stage. All of it will be useful at handover and, years later, if a question about a crack comes up.

The foundations are buried for good. The photo record is the only way to see how they were built.

Frequently asked questions

Who decides the type of foundation for a house?

A house's foundation type is chosen not by the owner but by the engineer, based on the geotechnical survey and structural calculations of the ground's real bearing capacity. Pad footings, strip footings, a raft or piles all follow from that calculation. A neighbour's raft proves nothing: two plots across the road from each other can differ greatly.

What should be planned into a house's foundation in advance?

Sleeves are set in the foundation at the right positions and depths for the water, electricity, telecoms and drainage connections and for pipes to the pool and garden. The earthing ring also goes in at this stage. Drilling cured concrete is not always possible and, where it is, it is expensive and needs the engineer's approval.

When is the best time to visit the site during foundation works?

The best time to visit during foundation works is the day the site's technical management inspects the reinforcement before the concrete pour. Bar diameters, spacing, cover and the anchorage of column starter bars are checked, and only then is concrete ordered. It is the last chance to see what ends up inside.

Which foundation records should you ask the contractor for?

Ask the contractor for photos of the reinforcement before the pour with a tape measure in shot, the concrete delivery notes with grade and delivery time, test results for any samples taken, and the technical management's notes on the stage. The foundation is buried for good, and this record is the only way to see how it was built.

Sources

Spanish Building Code (CTE), DB SE-C Foundations, section 3.1: geotechnical study

Spanish Building Code (CTE), DB SE-C Foundations, section 4.6.2: checks on the bearing ground

Spanish Building Code, Part I (Royal Decree 314/2006), art. 7.2.1: supply documentation

BCN YARD / Contact

Tell us what you have in mind.

Service area: Barcelona and the wider province.

  • Own crew and trusted subcontractors
  • We speak Russian and Spanish
  • Reply within an hour
  • Staged payments under contract
  1. 01Property
  2. 02Services
  3. 03Size and location
  4. 04Timing
  5. 05Contact
Property